| 24-hour TSP Monitoring Results |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Station AM3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Start |
Finish |
Weather |
Filter
Weight (g) |
Elapsed
Time Reading |
Sampling
Time |
Flow
Rate (m3/min) |
TSP Conc. |
Action
Level |
Limit Level |
Observations
/ Remarks |
Sampler |
Filter |
| Date |
Time |
Date |
Time |
|
Initial |
Final |
Initial |
Final |
(hrs) |
Initial |
Final |
Average |
(µg/m3) |
(µg/m3) |
(µg/m3) |
|
ID |
ID |
| 05-Nov-15 |
09:00 |
06-Nov-15 |
09:00 |
Sunny |
3.2483 |
3.4458 |
8784.20 |
8808.20 |
24.00 |
1.23 |
1.23 |
1.23 |
112 |
181 |
260 |
construction
work in progress |
TE-5170 A-01-48 |
150903/004 |
| 11-Nov-15 |
09:00 |
12-Nov-15 |
09:00 |
Sunny |
3.2797 |
3.4741 |
8808.20 |
8832.20 |
24.00 |
1.23 |
1.23 |
1.23 |
110 |
181 |
260 |
construction
work in progress |
TE-5170 A-01-48 |
151001/076 |
| 17-Nov-15 |
09:00 |
18-Nov-15 |
09:00 |
Cloudy |
3.2477 |
3.4551 |
8832.20 |
8856.20 |
24.00 |
1.22 |
1.22 |
1.22 |
118 |
181 |
260 |
Operation of
Mobile Crane |
TE-5170 A-01-48 |
150902/036 |
| 23-Nov-15 |
09:00 |
24-Nov-15 |
09:00 |
Sunny |
3.2654 |
3.5488 |
8856.20 |
8880.20 |
24.00 |
1.23 |
1.23 |
1.23 |
160 |
181 |
260 |
Operation of
Mobile Crane |
TE-5170 A-01-48 |
151101/027 |
| 27-Nov-15 |
09:00 |
28-Nov-15 |
09:00 |
Sunny |
3.2739 |
3.5698 |
8880.20 |
8904.20 |
24.00 |
1.24 |
1.24 |
1.24 |
166 |
181 |
260 |
Operation of
Mobile Crane |
TE-5170 A-01-48 |
151101/058 |
| 30-Oct-15 |
09:30 |
31-Oct-15 |
09:30 |
Sunny |
3.2235 |
3.3961 |
8760.20 |
8784.20 |
24.00 |
1.22 |
1.22 |
1.22 |
98 |
181 |
260 |
N.A. |
TE-5170 A-01-48 |
151001/042 |
|
|
|
|
|
|
|
|
|
|
|
|
Min. |
110 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Max. |
166 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Average |
133 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|